INDIAN OCEAN DRIVE
I refer to Indian Ocean Drive and the construction of the Lancelin-Cervantes section of this vital infrastructure. (1) When will tenders be called? (2) When will the contract be let? (3) What is the expected completion date? Hon ADELE FARINA

AnswerView source ↗

I thank the member for some notice of this question. (1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
(1) When will tenders be called? (2) When will the contract be let? (3) What is the expected completion date? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
(2) When will the contract be let? (3) What is the expected completion date? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
(3) What is the expected completion date? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
Hon ADELE FARINA replied: I thank the member for some notice of this question. (1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
I thank the member for some notice of this question. (1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
(1) The government’s commitment is to commence the first stage of the Lancelin-Cervantes road to Ocean Farms Estate in 2007-08. Contract documentation is being prepared with a view to calling tenders no later than June 2007. (2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
(2) It is intended to award a contract for the first stage no later than October 2007. (3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.
(3) It is anticipated that construction works on the first stage will be completed by the winter of 2008.