A WA parliamentary question seeks an update on the East Perth Power Station redevelopment, including its status, vesting, offers, selection process, current works, and planned works. The answer indicates strategic planning is underway, no entity is vested, no offers are being considered, and decommissioning/remediation work is occurring.

AnsweredQoN 901Legislative Assembly
Asked
12 September 2023
Portfolio
Planning; Lands; Housing; Homelessness

QuestionView source ↗

I refer to the East Perth Power Station Site Redevelopment, and I ask: (a) What is the current status of plans for the redevelopment of the East Perth Power Station site; (b) Has redevelopment of the site been vested in any entity (individual or company); (c) Are any offers to redevelop the site being considered by the Government; (d) What process is being, or was followed to select a party to redevelop the site; (e) What works are occurring on the site at present; and (f) Are any other works planned for the site in the coming 12 months?

AnswerView source ↗

Answered
12 October 2023
Responded by
Minister for Planning; Lands; Housing; Homelessness
Response time
8 days
(a)        DevelopmentWA is currently undertaking strategic planning of the East Perth Power Station.
(b-c)     No.
(d)       N/A.
(e-f)     Decommissioning, demolition and remediation of the Western Power Lot 601 Switchyard.