A parliamentary question regarding the staging and timeline for the release of housing lots in a $450 million joint venture project. The Minister's response provides general information but lacks specific details, deferring to the project control group's decisions.

AnsweredQoN 712Legislative Council
Asked
12 September 2006
Portfolio
Housing and Works

QuestionView source ↗

HOUSING LOTS - JOINT VENTURE PROJECT
I refer to the minister’s announcement of 3 September 2006 regarding a $450 million joint venture project to open a potential 2 600 housing lots. (1) How many stages will be involved in the release of those lots? (2) What is the proposed timetable for the release of each stage? (3) When will the first stage be available to the public? Hon KATE DOUST

AnswerView source ↗

I thank the member for some notice of this question. (1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
(1) How many stages will be involved in the release of those lots? (2) What is the proposed timetable for the release of each stage? (3) When will the first stage be available to the public? Hon KATE DOUST replied: I thank the member for some notice of this question. (1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
(2) What is the proposed timetable for the release of each stage? (3) When will the first stage be available to the public? Hon KATE DOUST replied: I thank the member for some notice of this question. (1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
(3) When will the first stage be available to the public? Hon KATE DOUST replied: I thank the member for some notice of this question. (1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
Hon KATE DOUST replied: I thank the member for some notice of this question. (1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
I thank the member for some notice of this question. (1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
(1) The staging strategy of the project will be agreed by the project control group, which comprises representatives of the joint venture partners. Five distinct neighbourhoods, a town centre, community facilities and a range of recreational activities and parkland reserves are proposed. (2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
(2) The staging strategy agreed by the project control group will include the proposed timing for release of each stage. (3) It is anticipated that the first home site will be available within two years.
(3) It is anticipated that the first home site will be available within two years.