A WA parliamentary question regarding the Esperance Regional Power Procurement process. The Minister's response indicates the process is still in the tender proposal stage, rendering further questions premature.

AnsweredQoN 789Legislative Assembly
Asked
10 October 2000
Member
Portfolio
Energy

QuestionView source ↗

(2) If so which tenders have reached the shortlist? (3) What would be the cost of providing energy per kilowatt? Answered on 14 November 2000 The Minister

AnswerView source ↗

Answered
14 November 2000
Response time
35 days
1. The Esperance Regional Power Procurement process is currently at the stage where the 12 consortia/companies are preparing their tender proposals. The closing date for submission of tenders is 24 October 2000. 2-3. Not applicable.
(3) What would be the cost of providing energy per kilowatt? Answered on 14 November 2000 The Minister Replied: 1. The Esperance Regional Power Procurement process is currently at the stage where the 12 consortia/companies are preparing their tender proposals. The closing date for submission of tenders is 24 October 2000. 2-3. Not applicable.
Answered on 14 November 2000 The Minister Replied: 1. The Esperance Regional Power Procurement process is currently at the stage where the 12 consortia/companies are preparing their tender proposals. The closing date for submission of tenders is 24 October 2000. 2-3. Not applicable.

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more