A WA parliamentary question probes the estimated costs, funding, and transparency surrounding the Perry Lakes Stadium Redevelopment, particularly regarding rugby facilities and potential cost overruns. The Minister provides limited information, deferring specifics until later stages of the project.

AnsweredQoN 1670Legislative Assembly
Asked
12 December 2006
Portfolio
Sport and Recreation

QuestionView source ↗

I refer to the Perry Lakes Stadium Redevelopment, and I ask –
(1) Will the Minister confirm that the estimated cost of the new Perry Lakes Stadium sporting facilities is $55.8 million?
(2) What is the estimated cost of building the rugby facilities on a separate site, given that an east-west flora corridor is to be retained on the new stadium site?
(3) Will the Government fund any scope increases or cost escalations relating to the project?
(4) Will the Minister provide a detailed breakdown of the final development budget prior to project commencement?
(5) When will the Minister release this information to Town of Cambridge ratepayers?

AnswerView source ↗

Answered
26 February 2007
Responded by
Minister for Sport and Recreation
Response time
76 days
(2) The costs are not yet determined. (3) The impact of escalation will not be determined until tenders have been received. The State is committed to funding 48 per cent of the State Athletics Centre. (4) Yes. (5) At an appropriate time, following finalisation of costings.
(3) The impact of escalation will not be determined until tenders have been received. The State is committed to funding 48 per cent of the State Athletics Centre. (4) Yes. (5) At an appropriate time, following finalisation of costings.
(4) Yes. (5) At an appropriate time, following finalisation of costings.
(5) At an appropriate time, following finalisation of costings.