A WA parliamentary question on notice regarding the progress, cost, and timeline of a 270km road construction project, broken into four stages. The response details completed work, current expenditure, budget allocations, and anticipated completion dates, while noting future stages are subject to budget considerations.

AnsweredQoN 359Legislative Assembly
Asked
17 August 2005
Portfolio
Planning and Infrastructure

QuestionView source ↗

(b) how many kilometres have been completed; (c) what is the estimated total cost; (d) what is the actual expenditure to date; (e) how much is allocated for construction in 2005-2006 and each of the forward estimate years; and (f) what is the anticipated completion date?
(c) what is the estimated total cost; (d) what is the actual expenditure to date; (e) how much is allocated for construction in 2005-2006 and each of the forward estimate years; and (f) what is the anticipated completion date?
(d) what is the actual expenditure to date; (e) how much is allocated for construction in 2005-2006 and each of the forward estimate years; and (f) what is the anticipated completion date?
(e) how much is allocated for construction in 2005-2006 and each of the forward estimate years; and (f) what is the anticipated completion date?
(f) what is the anticipated completion date?
(b) This project is being delivered in four stages. Stages 1, a length of 25 km (Tom Price to Nanutarra - Munjina Road) was competed and opened to traffic in December 2003 at a cost of $25.9 million. An Alliance contract for stage 2, a 90km length between Karratha and Baroowanna Hill was awarded on 19 August 2005 and is expected to be completed in 2008. (c) The current estimated cost to construct the entire route is $288 million. (d) Expenditure to 31 July 2005 was Stage 1 $25.9 million (completed) Stage 2 $2.2 million (in progress) (e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
An Alliance contract for stage 2, a 90km length between Karratha and Baroowanna Hill was awarded on 19 August 2005 and is expected to be completed in 2008. (c) The current estimated cost to construct the entire route is $288 million. (d) Expenditure to 31 July 2005 was Stage 1 $25.9 million (completed) Stage 2 $2.2 million (in progress) (e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
(c) The current estimated cost to construct the entire route is $288 million. (d) Expenditure to 31 July 2005 was Stage 1 $25.9 million (completed) Stage 2 $2.2 million (in progress) (e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
(d) Expenditure to 31 July 2005 was Stage 1 $25.9 million (completed) Stage 2 $2.2 million (in progress) (e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
Stage 1 $25.9 million (completed) Stage 2 $2.2 million (in progress) (e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
Stage 2 $2.2 million (in progress) (e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
(e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates: 2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
2005/06 12.9M 2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
2006/07 18.452M 2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
2007/08 17.1M 2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
2008/09 30.5M (f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.
(f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.

AnswerView source ↗

Answered
31 August 2005
Responded by
Minister for Planning and Infrastructure
Response time
14 days
(a) 270 kilometres
(b) This project is being delivered in four stages. Stages 1, a length of 25 km (Tom Price to Nanutarra - Munjina Road) was competed and opened to traffic in December 2003 at a cost of $25.9 million.
An Alliance contract for stage 2, a 90km length between Karratha and Baroowanna Hill was awarded on 19 August 2005 and is expected to be completed in 2008.
(c) The current estimated cost to construct the entire route is $288 million.
(d) Expenditure to 31 July 2005 was
Stage 1 $25.9 million (completed)
Stage 2 $2.2 million (in progress)
(e) The following allocations are provided for in the 2005/06 State Budget and Forward Estimates:
2005/06 12.9M
2006/07 18.452M
2007/08 17.1M
2008/09 30.5M
(f) Stage 2 is expected to be completed in 2008. Funding for the remaining stages 3 and 4 will be considered as part of the future State Budget considerations.