Question regarding Aboriginal site clearance for the Mount Henry Bridge project, specifically concerning the Bus Transit Way and Railway projects, and the relevant sections of the Aboriginal Heritage Act 1972. The Minister states the matter has not come before them.

AnsweredQoN 960Legislative Council
Asked
27 June 2003
Portfolio
Indigenous Affairs

QuestionView source ↗

With regard to the site clearance of the Mount Henry Bridge -
(1) When was the Mount Henry Bridge given Aboriginal site clearance for the Bus Transit Way project and under what part of the
Aboriginal Heritage Act 1972
was the site cleared and by whom?
(2) When was the Mount Henry Bridge given Aboriginal site clearance for the current Railway project and under what part of the
Aboriginal Heritage Act 1972
was the site cleared and by whom?

AnswerView source ↗

Answered
8 August 2003
Responded by
Minister for Housing and Works representing the Minister for Indigenous Affairs
Response time
42 days
(2) To date this matter has not come before the Minister for Indigenous Affairs.