Question regarding the construction of the Muchea Livestock Complex, specifically concerning the tender process, contract awarding, and expected completion date. The Minister provides detailed answers confirming the project's progress and budget adherence.

AnsweredQoN 258Legislative Council
Asked
18 March 2009
Portfolio
Agriculture and Food

QuestionView source ↗

MUCHEA LIVESTOCK COMPLEX — CONSTRUCTION
(1) Were tenders called for the construction of the Muchea Livestock Complex prior to the last election? (2) Have contracts been let as a result of that tender process? (3) If not, why have contracts not been let? (4) If contracts have been let, when were they let, and for what sum and to whom were they let? (5) When is it expected that the Muchea Livestock Complex will be available for use? Hon ROBYN McSWEENEY

AnswerView source ↗

I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(2) Have contracts been let as a result of that tender process? (3) If not, why have contracts not been let? (4) If contracts have been let, when were they let, and for what sum and to whom were they let? (5) When is it expected that the Muchea Livestock Complex will be available for use? Hon ROBYN McSWEENEY replied: I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(3) If not, why have contracts not been let? (4) If contracts have been let, when were they let, and for what sum and to whom were they let? (5) When is it expected that the Muchea Livestock Complex will be available for use? Hon ROBYN McSWEENEY replied: I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(4) If contracts have been let, when were they let, and for what sum and to whom were they let? (5) When is it expected that the Muchea Livestock Complex will be available for use? Hon ROBYN McSWEENEY replied: I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(5) When is it expected that the Muchea Livestock Complex will be available for use? Hon ROBYN McSWEENEY replied: I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
Hon ROBYN McSWEENEY replied: I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
I thank the honourable member for some notice of this question. The minister has provided the following answer — (1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(1) Yes; on 7 August 2008, a call for tenders for construction occurred. The deadline for submissions was 17 September 2008. The election occurred on 6 September 2008. (2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(2) Yes. (3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(3) Not applicable. (4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(4) Building company Cooper & Oxley Builders was awarded the construction contract on 14 November 2008. The construction contract is for $37.187 million. The total funding package of $54.54 million inclusive of the previous figure has been provided for the relocation of Midland saleyards. The total funding package covers all land, and previous and future construction costs. (5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.
(5) The new facility will be operational in early 2010. The construction program is running to schedule and budget.