A WA parliamentary question on notice regarding variations to the Narrows Bridge duplication project contract. The Minister for Transport provides a detailed breakdown of approved variations totaling $120,096 and states that no further variations have been sought by the contractor at this stage.

AnsweredQoN 68Legislative Council
Asked
16 August 2000
Portfolio
Transport

QuestionView source ↗

(1) Will the minister table a list of the variations that have been approved to the contract for the Narrows Bridge duplication project, and the costs for each of these variations? (2) Have any further variations been sought by the contractor which are yet to be approved, or are any anticipated? (3) If yes, will the minister table a list of these variations and their anticipated cost? Hon M.J. CRIDDLE

AnswerView source ↗

I thank the member for some notice of this question. (1) To date the current value of approved variations totals $120 096 and comprises: An unconditional undertaking for materials stored off site, $10 914; installation of additional settlement gauges, $18 240; provision of two additional monitoring piles, $18 200; supply and installation of additional granite pilasters, $12 142; design of different lane allocations on Mounts Bay Road ramp, $7 200; design of extension of northern road works, $30 000; and design of southern road works tie in, $23 400. (2)-(3) At this stage no other variations have been sought by the contractor.
(2) Have any further variations been sought by the contractor which are yet to be approved, or are any anticipated? (3) If yes, will the minister table a list of these variations and their anticipated cost? Hon M.J. CRIDDLE replied: I thank the member for some notice of this question. (1) To date the current value of approved variations totals $120 096 and comprises: An unconditional undertaking for materials stored off site, $10 914; installation of additional settlement gauges, $18 240; provision of two additional monitoring piles, $18 200; supply and installation of additional granite pilasters, $12 142; design of different lane allocations on Mounts Bay Road ramp, $7 200; design of extension of northern road works, $30 000; and design of southern road works tie in, $23 400. (2)-(3) At this stage no other variations have been sought by the contractor.
(3) If yes, will the minister table a list of these variations and their anticipated cost? Hon M.J. CRIDDLE replied: I thank the member for some notice of this question. (1) To date the current value of approved variations totals $120 096 and comprises: An unconditional undertaking for materials stored off site, $10 914; installation of additional settlement gauges, $18 240; provision of two additional monitoring piles, $18 200; supply and installation of additional granite pilasters, $12 142; design of different lane allocations on Mounts Bay Road ramp, $7 200; design of extension of northern road works, $30 000; and design of southern road works tie in, $23 400. (2)-(3) At this stage no other variations have been sought by the contractor.
Hon M.J. CRIDDLE replied: I thank the member for some notice of this question. (1) To date the current value of approved variations totals $120 096 and comprises: An unconditional undertaking for materials stored off site, $10 914; installation of additional settlement gauges, $18 240; provision of two additional monitoring piles, $18 200; supply and installation of additional granite pilasters, $12 142; design of different lane allocations on Mounts Bay Road ramp, $7 200; design of extension of northern road works, $30 000; and design of southern road works tie in, $23 400. (2)-(3) At this stage no other variations have been sought by the contractor.
I thank the member for some notice of this question. (1) To date the current value of approved variations totals $120 096 and comprises: An unconditional undertaking for materials stored off site, $10 914; installation of additional settlement gauges, $18 240; provision of two additional monitoring piles, $18 200; supply and installation of additional granite pilasters, $12 142; design of different lane allocations on Mounts Bay Road ramp, $7 200; design of extension of northern road works, $30 000; and design of southern road works tie in, $23 400. (2)-(3) At this stage no other variations have been sought by the contractor.
(1) To date the current value of approved variations totals $120 096 and comprises: An unconditional undertaking for materials stored off site, $10 914; installation of additional settlement gauges, $18 240; provision of two additional monitoring piles, $18 200; supply and installation of additional granite pilasters, $12 142; design of different lane allocations on Mounts Bay Road ramp, $7 200; design of extension of northern road works, $30 000; and design of southern road works tie in, $23 400. (2)-(3) At this stage no other variations have been sought by the contractor.
(2)-(3) At this stage no other variations have been sought by the contractor.