❓ This parliamentary question seeks information on the status, timelines, costs, and staging of the proposed Bunbury marine facilities project. The answer provides updates on completed and upcoming stages, the expected cost, and notes that staging is yet to be determined.
AnsweredQoN 1783Legislative Council
QuestionView source ↗
I refer to the proposal to build new marine facilities in Bunbury, and I ask: (a) what is the current status of the Bunbury marine facilities proposal; (b) what is the due date for the completion of the scoping study; (c) what is the expected completion date for the engineering and environmental studies; (d) what is the expected cost of the whole project; and (e) what is the proposed staging for the project?
AnswerView source ↗
Answered
2 December 2014
Responded by
Parliamentary Secretary representing the Minister for Regional Development
Response time
42 days
(a) An Environmental and Engineering Gap Analysis has been completed A Business Case for Environmental and Engineering Design has been prepared and submitted.
Casuarina master planning is due to commence.
(b) Completed.
(c) 30 December 2015.
(d) $46 million.
(e) To be determined.
Casuarina master planning is due to commence.
(b) Completed.
(c) 30 December 2015.
(d) $46 million.
(e) To be determined.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.