This parliamentary question seeks information on the status, timelines, costs, and staging of the proposed Bunbury marine facilities project. The answer provides updates on completed and upcoming stages, the expected cost, and notes that staging is yet to be determined.

AnsweredQoN 1783Legislative Council
Asked
21 October 2014
Portfolio
Regional Development

QuestionView source ↗

I refer to the proposal to build new marine facilities in Bunbury, and I ask: (a) what is the current status of the Bunbury marine facilities proposal; (b) what is the due date for the completion of the scoping study; (c) what is the expected completion date for the engineering and environmental studies; (d) what is the expected cost of the whole project; and (e) what is the proposed staging for the project?

AnswerView source ↗

Answered
2 December 2014
Responded by
Parliamentary Secretary representing the Minister for Regional Development
Response time
42 days
(a) An Environmental and Engineering Gap Analysis has been completed A Business Case for Environmental and Engineering Design has been prepared and submitted.
Casuarina master planning is due to commence.
(b) Completed.
(c)  30 December 2015.
(d) $46 million.
(e) To be determined.