❓ Mr. Love questions the Transport portfolio regarding the Jurien Bay Boat Harbour Breakwater Extension, including the program of works, reasons for delays, and project cost. The Minister responds that the project is progressing close to schedule and within budget.
AnsweredQoN 287Legislative Assembly
QuestionView source ↗
(1) Please outline the program of works to construct the Jurien Bay Boat Harbour Breakwater Extension ? (2) Why has this project been further delayed? (3) What is the expected cost of this project given the funding was announced 12 months ago?
AnswerView source ↗
Answered
16 September 2025
Responded by
Minister for Transport
Response time
9 days
1-3. Detailed design is due for completion by the end of 2025, and is progressing close to the original project timeframe.
The current estimated cost remains within the approved budget of $17.047million
The current estimated cost remains within the approved budget of $17.047million
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.