Hon Murray Criddle asks about contract variations and costs for each section of the Perth to Mandurah rail construction project. The Minister provides the number of variations and their approved values, stating costs will be covered by the project's contingency allowance.

AnsweredQoN 3361Legislative Council
Asked
22 March 2006
Portfolio
Planning and Infrastructure

QuestionView source ↗

I refer to the Government’s contracts on each section of the Perth to Mandurah rail construction project and ask -
(1) For each section (A to F) of the project, what variations has the Government agreed to on those contracts?
(2) For each section of the project can you please detail costs to date against the agreed variations?
(3) For each section of the project can you please provide an estimate of how far over or under the agreed variations you expect the final cost of the project to be?

AnswerView source ↗

Answered
4 May 2006
Responded by
Parliamentary Secretary representing the Minister for Planning and Infrastructure
Response time
43 days
Package No: Variations A 156 B 44 C 26 D 19 E 15 F 63 2. The value of variations currently approved for the major contracts under the Southern Suburbs Railway Packages is: Package Value $ A $4,271,954 B -$1,389,118 C -$1,691,990 D -$904,351 E $7,473,002 F $2,148,000 The cost of all variations will be accommodated within the project's contingency allowance, which is a component of the project budget.
2. The value of variations currently approved for the major contracts under the Southern Suburbs Railway Packages is: Package Value $ A $4,271,954 B -$1,389,118 C -$1,691,990 D -$904,351 E $7,473,002 F $2,148,000 The cost of all variations will be accommodated within the project's contingency allowance, which is a component of the project budget.
2. The value of variations currently approved for the major contracts under the Southern Suburbs Railway Packages is: Package Value $ A $4,271,954 B -$1,389,118 C -$1,691,990 D -$904,351 E $7,473,002 F $2,148,000 The cost of all variations will be accommodated within the project's contingency allowance, which is a component of the project budget.
Package Value $ A $4,271,954 B -$1,389,118 C -$1,691,990 D -$904,351 E $7,473,002 F $2,148,000 The cost of all variations will be accommodated within the project's contingency allowance, which is a component of the project budget.
The cost of all variations will be accommodated within the project's contingency allowance, which is a component of the project budget.