❓ Question regarding the status of the promised $18 million bridge to Treendale, including expenditure, completed works, and completion date. The answer provides updates on the tender process, expenditure, completed works, and expected completion date.
AnsweredQoN 4092Legislative Council
QuestionView source ↗
(1) What is the status of the promised $18 million bridge to Treendale? (2) What is the total funds expended on this project to date and what works have been completed? (3) When will the bridge be completed?
AnswerView source ↗
Answered
28 June 2016
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
61 days
(1) A tender for the works is expected to be advertised in July 2016, subject to final environmental approval.
(2) Expenditure to 23 May 2016 is $0.80 million. The following works have been completed:
(3) Second quarter 2018.
(2) Expenditure to 23 May 2016 is $0.80 million. The following works have been completed:
(3) Second quarter 2018.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.