Question regarding the status of the promised $18 million bridge to Treendale, including expenditure, completed works, and completion date. The answer provides updates on the tender process, expenditure, completed works, and expected completion date.

AnsweredQoN 4092Legislative Council
Asked
28 April 2016
Portfolio
Transport

QuestionView source ↗

(1) What is the status of the promised $18 million bridge to Treendale? (2) What is the total funds expended on this project to date and what works have been completed? (3) When will the bridge be completed?

AnswerView source ↗

Answered
28 June 2016
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
61 days
(1) A tender for the works is expected to be advertised in July 2016, subject to final environmental approval.
(2) Expenditure to 23 May 2016 is $0.80 million. The following works have been completed:
(3) Second quarter 2018.