Mr. Buswell inquires about the CADCOM project's expenditure and progress. The response details costs for planning, stages 1A/1B, and stage 1C, stating the project is on track within budget for 2007 completion.

AnsweredQoN 1732Legislative Assembly
Asked
12 December 2006
Portfolio
Police and Emergency Services

QuestionView source ↗

(1) How much to date has been spent on the implementation the CADCOM project?
(2) How far is the project currently off from its initial estimates and targets?

AnswerView source ↗

Answered
26 February 2007
Responded by
Minister for Police and Emergency Services
Response time
76 days
· Planning cost of $4.5m. · Stages 1A and 1B, the purchase of a new voice management and computer aided dispatch system, has been completed with a total cost of $17.6m. · Stage 1C, the new Perth Metropolitan Radio Network, (with an estimated total cost of $59.4m), $33.296m has been spent as at the end of November 2006. (2) The CADCOM project is on track for a successful full implementation during 2007 within its approved budget of $80.2m. Also an amount of $1.2m has been applied to the project from internal resources. This amount represents staff salaries associated with the Project.
· Stages 1A and 1B, the purchase of a new voice management and computer aided dispatch system, has been completed with a total cost of $17.6m. · Stage 1C, the new Perth Metropolitan Radio Network, (with an estimated total cost of $59.4m), $33.296m has been spent as at the end of November 2006. (2) The CADCOM project is on track for a successful full implementation during 2007 within its approved budget of $80.2m. Also an amount of $1.2m has been applied to the project from internal resources. This amount represents staff salaries associated with the Project.
· Stage 1C, the new Perth Metropolitan Radio Network, (with an estimated total cost of $59.4m), $33.296m has been spent as at the end of November 2006. (2) The CADCOM project is on track for a successful full implementation during 2007 within its approved budget of $80.2m. Also an amount of $1.2m has been applied to the project from internal resources. This amount represents staff salaries associated with the Project.
(2) The CADCOM project is on track for a successful full implementation during 2007 within its approved budget of $80.2m. Also an amount of $1.2m has been applied to the project from internal resources. This amount represents staff salaries associated with the Project.