Hon Martin Aldridge asks about the funding, timeline, cost, and local contractor involvement in the Geraldton Health Campus redevelopment. The parliamentary secretary provides figures for expenditure, projected dates, total cost, and number of local contractors engaged.

AnsweredQoN 123Legislative Council
Asked
20 February 2020
Portfolio
Health

QuestionView source ↗

GERALDTON HEALTH CAMPUS — REDEVELOPMENT
123. Hon MARTIN ALDRIDGE to the parliamentary secretary
representing the Minister for Health:
I
refer to the minister's media statement, ''Geraldton Health
Campus redevelopment underway'', from 9 January 2020.
(1) How much funding has been
expended to date on the Geraldton Health Campus redevelopment?
(2) What is the current expected
date for construction to commence and for project completion?
(3) What is the projected total cost
of the development?
(4) How many local contractors or
service providers have been engaged to date on the project?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1) As at 31 January 2020,
expenditure was $1 892 243.
(2) Construction is to commence in
mid-2020 and practical completion is expected by late 2023.
(3) The projected total cost is
$73.3 million.
(4) Two local contractors have been
engaged to date.