Hon Martin Aldridge asks about the scope, cost, and timeline of the Mullewa Primary Health Centre redevelopment. The answer details the facility's features, budget concerns due to market conditions, and construction timeline, but keeps budget deliberations confidential.

AnsweredQoN 459Legislative Council
Asked
15 December 2021
Portfolio
Health

QuestionView source ↗

I refer to the Mullewa Primary Health Centre redevelopment, I and ask: (a) what is the final scope of the redevelopment; (b) what is the final
expected cost of the redevelopment; (c) what is the expected
project timeline for the redevelopment; and (d) will this be
considered as part of the 2022-23 State Budget or Mid Year Review?

AnswerView source ↗

Answered
16 February 2022
Responded by
Minister representing the Minister for Health
Response time
3 days
(a)          A new build facility will include a contemporary emergency department; emergency telehealth service facilities; group therapy rooms; ambulatory care multipurpose consultation rooms and treatment spaces; an ambulance bay; short stay/respite palliative care; and a community supported home dialysis room.
(b)          The approved budget and funding for the project is $6.3 million, Given current market conditions, it is anticipated that the project will now exceed this allocation.
(c)          The Construction program (from tender award) is 55 weeks followed by another 11 weeks for demolition of old buildings.
(d)           Deliberations of ERC are Cabinet-in-confidence