Hon Samantha Rowe asks about the completion date of works on the Garratt Road Bridge in Ascot, following up on a previous question. The Parliamentary Secretary responds that the completion date was not met due to unforeseen deterioration and provides a new estimated completion date.

AnsweredQoN 238Legislative Council
Asked
17 March 2015
Portfolio
Transport

QuestionView source ↗

GARRATT
ROAD BRIDGE
238. Hon SAMANTHA ROWE to the
parliamentary secretary representing the Minister for Transport:
I refer to the works being carried out by Main Roads on the
Garratt Road Bridge in Ascot and the Minister for TransportXXX ###XXXs
response to question without notice 10.
(1) Has the completion date for the works of 15 March been
met?
(2) If not, why not; and what is the new estimated completion
date?

AnswerView source ↗

I thank the member
for some notice of this question.
(1)–(2) The third and final section
of the footpath replacement involved more work than was originally envisaged,
as greater deterioration of the supporting timber became evident once the final
section of existing concrete footpath was lifted. It is due to be completed by
the end of March.