Question regarding the delayed upgrade of the Roe Highway-Berkshire Road intersection, originally announced in 2012 with construction planned for 2013-14. The response indicates design and tender work is progressing, with construction anticipated to begin in 2014-15 and be completed in 2015.

AnsweredQoN 544Legislative Council
Asked
13 May 2014
Portfolio
Transport

QuestionView source ↗

ROE
HIGHWAY–BERKSHIRE ROAD INTERSECTION
544. Hon SAMANTHA ROWE to the
parliamentary secretary representing the Minister for Transport:
In 2012 the government announced a $15 million upgrade to the
dangerous Roe Highway–Berkshire Road intersection, with construction to
begin in the 2013–14 financial year.
(1) Has construction commenced on
the upgrade?
(2) If no to (1), why has the
commencement been delayed?
(3) If no to (1), when will
construction commence?
(4) When will the upgrade be
complete?

AnswerView source ↗

I thank the honourable member for
some notice of this question.
(1)–(4) Design
and tender documentation work is well advanced and will be completed by the end
of the current financial year. Construction is anticipated to commence during
the 2014–15 financial year, and be completed in 2015.