Question regarding road upgrades needed between Cunderdin and Quairading due to the closure of tier three rail lines, with details on works, costs, and timelines provided by Main Roads WA.

AnsweredQoN 4537Legislative Council
Asked
17 August 2011
Portfolio
Transport

QuestionView source ↗

(1) Will the road between Cunderdin and Quairading require any upgrade as a result of the decision to cease operations on the tier three rail lines?
(2) If yes to (1), what works are required?
(3) What is the estimated cost of these works?
(4) When will the work commence?
(5) When will the work be completed?

AnswerView source ↗

Answered
21 September 2011
Responded by
Minister for Finance representing the Minister for Transport
Response time
35 days
Main Roads Western Australia advises:
(1) Yes
(2) Roads works including sealing and other improvements.
(3)  $9.70m
(4) Some has been completed, some has begun and some will start in 2012-13.
(5) 2012-13 and 2013-14.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more