Hon. C.L. Edwardes asks about the tender process and timeline for the Greenwood, Clarkson, and Currambine train stations. The Minister provides specific dates for tender issuance, contract awards, and construction completion, confirming the September 2003 service commencement target.

AnsweredQoN 992Legislative Assembly
Asked
30 August 2001
Portfolio
Planning and Infrastructure

QuestionView source ↗

(1) Have the tenders been let for the Greenwood, Clarkson and Currambine train stations, and if so, on what date?
(2) If not, what date is this expected to happen?
(3) Are the services to the above stations, still scheduled to begin in September 2003, as per your Media Release of the 2 May 2001?

AnswerView source ↗

Answered
16 October 2001
Responded by
Minister for Planning and Infrastructure
Response time
47 days
(2) Tender Documents will be issued to pre-qualified tenderers as follows : Currambine: 29 October, 2001 Clarkson: 6 February, 2002 Greenwood: 28 May, 2002 Contracts are expected to be awarded at the latest by the following dates : Currambine: 5 February, 2002 Clarkson: 21 May, 2002 Greenwood: 3 September, 2002 (3) Yes. Construction is expected to be completed as follows : Currambine: March 2003 Clarkson: April 2003 Greenwood: July 2003
Currambine: 29 October, 2001 Clarkson: 6 February, 2002 Greenwood: 28 May, 2002 Contracts are expected to be awarded at the latest by the following dates : Currambine: 5 February, 2002 Clarkson: 21 May, 2002 Greenwood: 3 September, 2002 (3) Yes. Construction is expected to be completed as follows : Currambine: March 2003 Clarkson: April 2003 Greenwood: July 2003
Contracts are expected to be awarded at the latest by the following dates : Currambine: 5 February, 2002 Clarkson: 21 May, 2002 Greenwood: 3 September, 2002 (3) Yes. Construction is expected to be completed as follows : Currambine: March 2003 Clarkson: April 2003 Greenwood: July 2003
Currambine: 5 February, 2002 Clarkson: 21 May, 2002 Greenwood: 3 September, 2002 (3) Yes. Construction is expected to be completed as follows : Currambine: March 2003 Clarkson: April 2003 Greenwood: July 2003
(3) Yes. Construction is expected to be completed as follows : Currambine: March 2003 Clarkson: April 2003 Greenwood: July 2003
Currambine: March 2003 Clarkson: April 2003 Greenwood: July 2003