❓ A WA parliamentary question regarding planned upgrades to intersections and road construction in the Pilbara region, specifically near Port Hedland. The Minister confirms the upgrades will proceed as planned and provides timelines for tender, commencement, and completion.
AnsweredQoN 48Legislative Assembly
QuestionView source ↗
(2) Will upgrading in this area still include the previously planned and agreed upgrades to
(a) intersections Pinga and Wallwork Road;
(b) the construction of a 4
th
lane from Wallwork to Port Hedland turn off; and
(c) the completion of overall works on the Broome turnoff, including improved left turn off lane towards South Hedland to make two lanes to make two lanes to turn off into Wallwork Road and the Shell road house – without any reduction of the allocated state funds?
(3) When will this work go out to tender?
(4) When is it anticipated the works will commence and be completed?
(a) intersections Pinga and Wallwork Road;
(b) the construction of a 4
th
lane from Wallwork to Port Hedland turn off; and
(c) the completion of overall works on the Broome turnoff, including improved left turn off lane towards South Hedland to make two lanes to make two lanes to turn off into Wallwork Road and the Shell road house – without any reduction of the allocated state funds?
(3) When will this work go out to tender?
(4) When is it anticipated the works will commence and be completed?
AnswerView source ↗
Answered
1 December 2008
Responded by
Minister representing the Minister for Transport
Response time
20 days
(1) Total allocation - $12.036 million as follows:
2008/09 - $11.592 million
2009/10 - $0.442 million
(2) (a) Yes
(b) Yes
(c) Yes
(3) It is currently anticipated the works will go out to tender in December 2008.
(4) It is currently anticipated the works will commence in February / March 2009 and be completed in August 2009.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
2008/09 - $11.592 million
2009/10 - $0.442 million
(2) (a) Yes
(b) Yes
(c) Yes
(3) It is currently anticipated the works will go out to tender in December 2008.
(4) It is currently anticipated the works will commence in February / March 2009 and be completed in August 2009.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.