Question regarding the planning, timeline, and budget for a priority bicycle link alongside the Mitchell Freeway from Glendalough to Balcatta, with a detailed response provided by the Minister for Transport.

AnsweredQoN 1829Legislative Council
Asked
21 October 2014
Portfolio
Transport

QuestionView source ↗

I refer to the Western Australia Bicycle Network Plan and ask, for the priority link alongside the Mitchell Freeway from Glendalough to Balcatta: (a) what planning work has been done on this link; (b) what are the details of the works required; (c) when does the Minister expect work to commence; (d) when does the Minister expect works to be completed; (e) what is the estimated cost of this project; and (f) how much is currently allocated in the 2014-15 State Budget and in each year of the forward estimates?

AnswerView source ↗

Answered
3 December 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
43 days
(a-b) It is proposed to install a Principal Shared Path and associated structures. Planning works include:
· concept design.
· detailed design.
· an alignment study.
(c-d) The section is complete with future works scheduled to commence in late 2016 and be completed in 2017.
(e) The estimated cost is $5.675million for scheduled works. The cost estimate for remaining works will be developed after the designs have been completed.
(f)
2014-15-$2.625 million
2016-17 - $2.825 million