Hon Ken Travers asked about the platform extension at Loch and Grant Street train stations. Hon Simon O’Brien confirmed the project, its status, budget spent, and total cost.

AnsweredQoN 206Legislative Council
Asked
11 March 2009
Portfolio
Transport

QuestionView source ↗

RAILWAY STATIONS — LOCH AND GRANT STREETS
(1) Can the minister confirm that the platforms are to be extended at the Loch and Grant Street train stations? (2) If yes to (1), what is the current status of works? (3) How much of the budget has already been spent? (4) What is the total cost of the proposed works? Hon SIMON O’BRIEN

AnswerView source ↗

I thank the honourable member for some notice of the question. (1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(2) If yes to (1), what is the current status of works? (3) How much of the budget has already been spent? (4) What is the total cost of the proposed works? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of the question. (1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(3) How much of the budget has already been spent? (4) What is the total cost of the proposed works? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of the question. (1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(4) What is the total cost of the proposed works? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of the question. (1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of the question. (1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
I thank the honourable member for some notice of the question. (1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(1) Yes. (2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(2) Loch Street has 15 per cent of works completed and Grant Street has five per cent of works completed. (3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(3) A total of $150 000 has already been spent. (4) The total cost of the proposed works is $950 000.
(4) The total cost of the proposed works is $950 000.