Question regarding the Geraldton harbour deepening project. While the project is on budget, the completion date is likely to be delayed due to weather conditions, pushing it to the end of October instead of August 31st.

AnsweredQoN 1035Legislative Council
Asked
25 June 2003
Portfolio
Planning and Infrastructure

QuestionView source ↗

Will the minister confirm that the deepening of the Geraldton harbour and channel is on time and on budget at this date? Hon GRAHAM GIFFARD

AnswerView source ↗

I thank the member for some notice of this question. The contract date for practical completion of dredging remains 31 August 2003. The minister is advised that dredging is over 75 per cent completed. The contractor has indicated that it believes it will be difficult to achieve the contracted date. The port authority is continuing to work with the contractor to assist it to meet its obligation, and the minister is advised that the interests of the port and the community will be appropriately protected under the contract in the event of delay. The actual end date will be dependent on weather and sea state but we are now working on a completion at the end of October. The minister has further advised that the project is on budget.
Hon GRAHAM GIFFARD replied: I thank the member for some notice of this question. The contract date for practical completion of dredging remains 31 August 2003. The minister is advised that dredging is over 75 per cent completed. The contractor has indicated that it believes it will be difficult to achieve the contracted date. The port authority is continuing to work with the contractor to assist it to meet its obligation, and the minister is advised that the interests of the port and the community will be appropriately protected under the contract in the event of delay. The actual end date will be dependent on weather and sea state but we are now working on a completion at the end of October. The minister has further advised that the project is on budget.
I thank the member for some notice of this question. The contract date for practical completion of dredging remains 31 August 2003. The minister is advised that dredging is over 75 per cent completed. The contractor has indicated that it believes it will be difficult to achieve the contracted date. The port authority is continuing to work with the contractor to assist it to meet its obligation, and the minister is advised that the interests of the port and the community will be appropriately protected under the contract in the event of delay. The actual end date will be dependent on weather and sea state but we are now working on a completion at the end of October. The minister has further advised that the project is on budget.
The contract date for practical completion of dredging remains 31 August 2003. The minister is advised that dredging is over 75 per cent completed. The contractor has indicated that it believes it will be difficult to achieve the contracted date. The port authority is continuing to work with the contractor to assist it to meet its obligation, and the minister is advised that the interests of the port and the community will be appropriately protected under the contract in the event of delay. The actual end date will be dependent on weather and sea state but we are now working on a completion at the end of October. The minister has further advised that the project is on budget.