A WA parliamentary question seeks a breakdown of costs associated with the Perth Stadium taskforce, including land acquisition, staffing, and other related expenses. The answer provides figures for taskforce reports, valuations, and current year staff and associated costs.

AnsweredQoN 516Legislative Assembly
Asked
10 March 2009
Portfolio
Housing and Works

QuestionView source ↗

(a) all costs associated with the Stadium taskforce;
(b) cost of acquiring any homes in the area;
(c) staff costs; and
(d) any other associated costs, including legal costs?

AnswerView source ↗

Answered
7 April 2009
Responded by
Minister for Housing and Works
Response time
28 days
(a) Costs associated with the Stadium taskforce in producing the interim and final taskforce reports over the 2005/06 and 2006/07 financial years, was in the order of $1.695 million. These costs were met from Department of Sport and Recreation internal resourcing and appropriations over the 2005/06 and 2006/07 financial years.
(b) No homes have been acquired for the Perth Stadium project, however valuations have been obtained through the Department of Land Information at a cost of $5,600.
(c) Further to those costs included in (1) above, staff costs for the current financial year have been $417,080.
(d) Further to those costs included in (1) above, associated costs are $527,324 for the current financial year
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more