Hon Martin Aldridge asks about the Bindoon Bypass project, including update timelines, funding details, and expected completion date. The Minister's response indicates the project is under review, delaying further updates.

AnsweredQoN 1509Legislative Council
Asked
9 August 2023
Portfolio
Transport

QuestionView source ↗

I refer to the Bindoon Bypass on the Great Northern Highway, and I ask: (a) noting the most recent project update was published in July 2022, when will Main Roads provide the community with an update on the progress and status of this project; (b) what is the total value of this project and what is the State Government's contribution towards this project; and (c) what is the expected completion date for this project?

AnswerView source ↗

Answered
12 September 2023
Responded by
Minister for Emergency Services representing the Minister for Transport
Response time
8 days
(a)-(c)  The current funding allocated to the Bindoon Bypass is $275 million, which includes a State Government contribution of $55 million.
The project is subject to the “Commonwealth Infrastructure Investment Program 90 Day Strategic Review”.  Following completion of the Review, a procurement timeframe and further updates to the community will be provided.