❓ Mr. Johnston requests operational data for the Muja AB power plant units for July-August 2015, specifically hours of operation and energy delivered. The answer indicates all units were offline during that period.
AnsweredQoN 4540Legislative Assembly
QuestionView source ↗
I refer to the answer to the question on notice 1936 answered on 6 May 2014 and I ask for the following information for each of the Muja AB units: (a) for each unit, 1, 2, 3, 4, that make up Muja AB, please provide the following information for the period from 1 July 2015 to 31 August 2015: (i) how many hours they have been used; and (ii) the total amount of energy that has been delivered into the network?
AnswerView source ↗
Answered
13 October 2015
Responded by
Minister for Energy
Response time
33 days
(a)
(i - ii) See table below.
Hours Operation from 1 July 2015 to 31 August 2015
Total Energy Sent Out from 1 July 2015 to 31 August 2015 (MWh)
Muja_G1
0
0.00
Muja_G2
0
0.00
Muja_G3
0
0.00
Muja_G4
0
0.00
(i - ii) See table below.
Hours Operation from 1 July 2015 to 31 August 2015
Total Energy Sent Out from 1 July 2015 to 31 August 2015 (MWh)
Muja_G1
0
0.00
Muja_G2
0
0.00
Muja_G3
0
0.00
Muja_G4
0
0.00
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.