❓ Question regarding the partial completion of the Preston River Relocation Design as stated in the Southern Ports Authority 2016 Annual Report, seeking reasons for partial completion and expected completion date. The answer cites stakeholder input as the reason for delay.
AnsweredQoN 4461Legislative Council
QuestionView source ↗
I refer to the Southern Ports Authority 2016 Annual Report , which states the Preston River Relocation Design was partially completed, and I ask: (a) why was the design only partially completed; and (b) what is the expected completion date for the design work?
AnswerView source ↗
Answered
16 November 2016
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
36 days
The Southern Ports Authority advises:
(a) The Southern Ports Authority is waiting on stakeholder input.
(b) The design work is provisionally completed and final completion depends on stakeholder input.
(a) The Southern Ports Authority is waiting on stakeholder input.
(b) The design work is provisionally completed and final completion depends on stakeholder input.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.