I refer to the Major Stadia Taskforce report that identified that an estimated 20,760 passengers could travel to and from events at the Burswood Peninsula site on 28 trains, and ask - (1)

AnsweredQoN 5272Legislative Council
Asked
8 March 2012
Portfolio
Transport

QuestionView source ↗

I refer to the Major Stadia Taskforce report that identified that an estimated 20,760 passengers could travel to and from events at the Burswood Peninsula site on 28 trains, and ask -
(1) How was it determined that 28 trains would be required?
(2) What modelling was undertaken to ensure that moving 20,760 passengers could be achieved?

AnswerView source ↗

Answered
1 May 2012
Responded by
Minister for Finance representing the Minister for Transport
Response time
54 days
The Public Transport Authority advises:
(1 - 2) A Master Plan, will be completed in the first half of 2013. It will include the provisions and cost estimates for road, rail, bus facilities and the pedestrian bridge. It is assumed the information referred to by the Member relates to statements made in the Legislative Assembly on 22 Feb 2012. The statement was made on advice from the Public Transport Authority and only planned passenger numbers were advised. A Master Plan for this service is being developed and specific information will be made public as appropriate once it has been considered.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more