Question on Notice regarding the Bunbury Taskforce, its terms of reference, budget, reporting date, personnel, and public release of its report. The Taskforce reviewed health services in Bunbury and identified strategies for improvement.

AnsweredQoN 1549Legislative Assembly
Asked
20 February 2002
Member
Portfolio
Health

QuestionView source ↗

(b) what are the terms of reference of each task force; (c) does each task force have its own budget; (d) if the answer to (c) is yes, how much is the budget for each task force; (e) if the answer to (c) is no, how are the costs of each task force being met, and what is the cost of each task force; (f) on what date is each task force required to report; (g) who is the chair of each task force; (h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(c) does each task force have its own budget; (d) if the answer to (c) is yes, how much is the budget for each task force; (e) if the answer to (c) is no, how are the costs of each task force being met, and what is the cost of each task force; (f) on what date is each task force required to report; (g) who is the chair of each task force; (h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(d) if the answer to (c) is yes, how much is the budget for each task force; (e) if the answer to (c) is no, how are the costs of each task force being met, and what is the cost of each task force; (f) on what date is each task force required to report; (g) who is the chair of each task force; (h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(e) if the answer to (c) is no, how are the costs of each task force being met, and what is the cost of each task force; (f) on what date is each task force required to report; (g) who is the chair of each task force; (h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(f) on what date is each task force required to report; (g) who is the chair of each task force; (h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(g) who is the chair of each task force; (h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(h) are any other Members of Parliament involved with the task force; (i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(i) if the answer to (h) is yes, which particular members are involved; (j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(j) will the reports of each task force be made public; (k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(k) if the answer to (j) is yes, how will each task force report be released to the public; and (l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(l) if the answer to (j) is no, what are the reasons for not releasing the reports of each task force?
(b) (1) Review hospital and public health services available to the public in Bunbury, including : a) Availability of beds, including maternity beds b) Waiting times for patients in Casualty; and c) Staff shortages at critical times (2) Review current and future levels of post acute care services. (3) Identify strategies to attract specialist doctors to Bunbury. (4) Review the introduction of rehabilitation services at the South-West Health Campus including restorative care services for older people. (5) Identify strategies to ensure adequate supply of nurses and support personnel to the South West Health Campus. (c) Yes (d) $300,000 was budgeted. The actual cost was $84,932.70. (e) Not applicable (f) The Bunbury Taskforce was required to report by 31 December 2001. (g) Tony Dean MLA (h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(c) Yes (d) $300,000 was budgeted. The actual cost was $84,932.70. (e) Not applicable (f) The Bunbury Taskforce was required to report by 31 December 2001. (g) Tony Dean MLA (h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(d) $300,000 was budgeted. The actual cost was $84,932.70. (e) Not applicable (f) The Bunbury Taskforce was required to report by 31 December 2001. (g) Tony Dean MLA (h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(e) Not applicable (f) The Bunbury Taskforce was required to report by 31 December 2001. (g) Tony Dean MLA (h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(f) The Bunbury Taskforce was required to report by 31 December 2001. (g) Tony Dean MLA (h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(g) Tony Dean MLA (h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(h) Yes (i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(i) Hon Ljiljanna Ravlich MLC (j) Yes (k) Tabled in Parliament (l) Not applicable
(j) Yes (k) Tabled in Parliament (l) Not applicable
(k) Tabled in Parliament (l) Not applicable
(l) Not applicable

AnswerView source ↗

Answered
22 May 2002
Responded by
Minister for Health
Response time
91 days
(a) Bunbury Taskforce
(b) (1) Review hospital and public health services available to the public in Bunbury, including
:
a) Availability of beds, including maternity beds
b) Waiting times for patients in Casualty; and
c) Staff shortages at critical times
(2) Review current and future levels of post acute care services.
(3) Identify strategies to attract specialist doctors to Bunbury.
(4) Review the introduction of rehabilitation services at the South-West Health Campus including restorative care services for older people.
(5) Identify strategies to ensure adequate supply of nurses and support personnel to the South West Health Campus.
(c) Yes
(d) $300,000 was budgeted. The actual cost was $84,932.70.
(e) Not applicable
(f) The Bunbury Taskforce was required to report by 31 December 2001.
(g) Tony Dean MLA
(h) Yes
(i) Hon Ljiljanna Ravlich MLC
(j) Yes
(k) Tabled in Parliament
(l) Not applicable