Hon Ken Travers asks about the expected and current completion dates for the Esperance Port access road, revealing funding gaps and reliance on private investment.

AnsweredQoN 1912Legislative Council
Asked
3 March 2010
Portfolio
Transport

QuestionView source ↗

(1) When funding was provided in the 2008/09 budget, what was the expected completion date of the Esperance Port access road?
(2) What is the current completion date of the Esperance Port access road?

AnswerView source ↗

Answered
20 April 2010
Responded by
Minister for Transport
Response time
48 days
(1) An amount of $8m was provided in the 2008-09 State Budget for planning and preconstruction works. No funding was allocated within the Forward Estimates for construction.
(2)State funding will be provided in a future Budget process and completion will depend on the required one third private contribution being identified.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more