Question regarding the commencement, duration, and mitigation strategies for roadworks on Reid Highway west of Erindale Road. The Minister provides a timeline and outlines measures to minimise traffic disruption.

AnsweredQoN 3978Legislative Assembly
Asked
21 April 2015
Portfolio
Transport

QuestionView source ↗

Can the Minister advise when promised roadworks to Reid Highway west of Erindale Road will commence, and what the estimated duration of these works and what measures will be taken during the currency of the roadworks to ameliorate increased delays and congestion?

AnswerView source ↗

Answered
11 August 2015
Responded by
Minister for Transport
Response time
112 days
Site works are expected to commence mid-2015. All construction works are expected to be completed by mid-2016.
Main Roads will work closely with the contractor to develop construction staging and associated temporary traffic management arrangements which seek to minimise delays and congestion.
Measures will include:
· Providing advance notice of temporary traffic management arrangements (newspapers, letter drop, construction reference group etc.);
· Utilising night time / off-peak works where appropriate;
· Limiting the temporary closure of traffic lanes;
· No temporary lane closures on Mitchell Freeway during peak times;
· Making special provision for sports events, cultural events and public holiday weekends; and
· Adopting construction methods and techniques which minimise the duration of construction impacts.