Question regarding the delayed extension of the 450 bus route in Landsdale, with the government providing context on overall bus service investment and outlining the proposed route extension.

AnsweredQoN 4875Legislative Assembly
Asked
16 February 2016
Portfolio
Transport

QuestionView source ↗

I refer to information provided in answer to supplementary question A29 of the Estimates hearing on 9 June 2015 in respect to improved bus services in the Landsdale area and ask: (a) when will the extension of the 450 bus route commence; (b) what are the reasons for the delay; and (c) what is the new proposed route?

AnswerView source ↗

Answered
17 March 2016
Responded by
Minister for Transport
Response time
30 days
(a)-(b) In 2011, the Liberal-National Government commenced the biggest investment in bus service kilometres ever experienced in this State in a condensed period. This investment has progressively grown to a point where over 13.5 million additional annual service kilometres, a measure of both service frequency and network coverage, were provided in 2014/15 representing a growth of over 26 per cent when compared to 2008/09.
This investment has continued through 2015/16 with over 800,000 additional annual service kilometres to be added to the network by the end of the 2015/16 financial year.
Whilst this remains a priority service development for Transperth, a commencement date has not been set.
(c) The proposed extension will see the bus route 450 service extend east along Kingsway before terminating in the vicinity of Pomodora Avenue, Landsdale.