❓ (1) Can the Minister advise what progress has been made on the installation of the police regional radio network? (2) Have committee deliberations been concluded? (3) When is it anticipated installati
AnsweredQoN 4709Legislative Assembly
QuestionView source ↗
(1) Can the Minister advise what progress has been made on the installation of the police regional radio network?
(2) Have committee deliberations been concluded?
(3) When is it anticipated installation will be finalised?
(4) What is the anticipated cost?
(2) Have committee deliberations been concluded?
(3) When is it anticipated installation will be finalised?
(4) What is the anticipated cost?
AnswerView source ↗
Answered
21 March 2011
Responded by
Minister for Police
Response time
25 days
1. The CSN-RRN Project (Community Safety Network - Regional Radio Network) is currently progressing through procurement stages of 3 separate requests.
Component A - Conventional Digital Radio Network - An Open Market Request has closed and evaluations will conclude towards mid May 2011. Implementation is scheduled to commence in the 4th week of July 2011.
Component B - Trunked Radio Network (Sole Supplier) - Requests for this component have closed and evaluations are under way. Implementation is scheduled to commence in the 1st week of June 2011.
Component C - Digital Terminal Equipment (Sole Supplier) - Requests for this component have closed and evaluations are under way. This component is scheduled to be delivered from June 2011.
In addition to these requests, Western Australia Police are undertaking management of Site Infrastructure Services (Component D) to ensure radio tower sites are compliant, secure and ready for network implementation. WA Police are working with existing contractors, Department of Treasury and Finance Building Management and Works (BMW) and radio site owners to progress these activities. This component is progressing at a number of locations throughout Regional WA.
2. WA Police cannot provide a response without being advised of which committee this refers to.
3. Component A - Conventional Digital Radio Network will be delivered over a 5 year period and is scheduled for completion in 2016.
Component B - Trunked Radio Network will be delivered over an 18 month period and is scheduled for completion in early 2013.
Component C - Digital Terminal Equipment will be deployed over an 18 month period with the bulk completed by mid 2012.
4. The cost to WA Police is estimated at $71.1 million capital.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Component A - Conventional Digital Radio Network - An Open Market Request has closed and evaluations will conclude towards mid May 2011. Implementation is scheduled to commence in the 4th week of July 2011.
Component B - Trunked Radio Network (Sole Supplier) - Requests for this component have closed and evaluations are under way. Implementation is scheduled to commence in the 1st week of June 2011.
Component C - Digital Terminal Equipment (Sole Supplier) - Requests for this component have closed and evaluations are under way. This component is scheduled to be delivered from June 2011.
In addition to these requests, Western Australia Police are undertaking management of Site Infrastructure Services (Component D) to ensure radio tower sites are compliant, secure and ready for network implementation. WA Police are working with existing contractors, Department of Treasury and Finance Building Management and Works (BMW) and radio site owners to progress these activities. This component is progressing at a number of locations throughout Regional WA.
2. WA Police cannot provide a response without being advised of which committee this refers to.
3. Component A - Conventional Digital Radio Network will be delivered over a 5 year period and is scheduled for completion in 2016.
Component B - Trunked Radio Network will be delivered over an 18 month period and is scheduled for completion in early 2013.
Component C - Digital Terminal Equipment will be deployed over an 18 month period with the bulk completed by mid 2012.
4. The cost to WA Police is estimated at $71.1 million capital.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.