Hon. Sally Talbot asks about the Denmark community wind farm's completion deadline and financial viability. Hon. Peter Collier responds that the Office of Energy is seeking further information to assess project risks and viability, acknowledging differing opinions on the project.

AnsweredQoN 943Legislative Council
Asked
17 November 2010
Portfolio
Energy

QuestionView source ↗

DENMARK COMMUNITY WIND FARM
(1) Has the Office of Energy made a submission to the commonwealth government seeking an extension to the completion deadline for the Denmark community wind farm? (2) Does the Office of Energy believe that the Denmark community wind farm is able to complete the project within a reasonable time frame and that the project remains financially viable? (3) If yes to (2), what is the Office of Energy doing to progress the Denmark community wind farm’s grants application? Hon PETER COLLIER

AnswerView source ↗

I thank the honourable member for some notice of the question. (1) Yes. (2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.
(2) Does the Office of Energy believe that the Denmark community wind farm is able to complete the project within a reasonable time frame and that the project remains financially viable? (3) If yes to (2), what is the Office of Energy doing to progress the Denmark community wind farm’s grants application? Hon PETER COLLIER replied: I thank the honourable member for some notice of the question. (1) Yes. (2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.
(3) If yes to (2), what is the Office of Energy doing to progress the Denmark community wind farm’s grants application? Hon PETER COLLIER replied: I thank the honourable member for some notice of the question. (1) Yes. (2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.
Hon PETER COLLIER replied: I thank the honourable member for some notice of the question. (1) Yes. (2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.
I thank the honourable member for some notice of the question. (1) Yes. (2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.
(1) Yes. (2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.
(2)–(3) The Office of Energy is currently seeking additional information about the project to assess the project risks, including whether it can be completed in a reasonable time frame and whether it remains financially viable. As the member will be aware, there is a great divergence of opinion about that wind farm, so we will continue to work through it.