Mrs. Harvey inquires about the completion status and costs of the Fremantle Passenger Terminal upgrades announced in March 2018. The Minister confirms the upgrades are not yet complete but are on schedule for December 2018, and provides a cost breakdown.

AnsweredQoN 4049Legislative Assembly
Asked
13 September 2018
Portfolio
Transport

QuestionView source ↗

I refer to the media release dated 11 March 2018 titled Fremantle Passenger Terminal to get $3 million upgrade, and I ask: (a) are the upgrades to the terminal now completed; (b) if no to (a) why not, and when are the upgrades expected to be completed; and (c) will the Minister table a list with a breakdown of the costs of the upgrades?

AnswerView source ↗

Answered
16 October 2018
Responded by
Minister for Transport
Response time
7 days
(a) No
(b) The Scheduled completion date is December 2018. Works are progressing to schedule.
(c) Estimated Costs: Security Screens and External Canopy - $1,330,000; Painting - $1,050,000; Foyer Refurbishment - $320,000; General Refurbishment - $290,000; Furniture - $150,000; Signage - $40,000