A WA parliamentary question seeks information on the release date of an inquiry into fatal accidents at BHP Billiton's Port Hedland HBI plant and the proposed schedule for recommencement of production. The Minister advises the report is due 30 November 2004 and recommencement depends on the report's findings.

AnsweredQoN 943Legislative Council
Asked
10 November 2004
Portfolio
State Development

QuestionView source ↗

(1) Will the minister confirm the release date of the inquiry into the fatal accidents at BHP Billiton’s hot briquetted iron plant in Port Hedland? (2) Will the minister inform the House about the proposed schedule for the recommencement of production of the HBI plant in Port Hedland? Hon KEN TRAVERS

AnswerView source ↗

I thank the member for some notice of this question. I am advised - (1) The report requisitioned by the State Mining Engineer from Boodarie Iron, under section 45 of the Mines Safety and Inspection Act 1994, is currently due to be submitted on 30 November 2004. (2) Recommencement by Boodarie Iron of production from the HBI plant will be dependent upon full consideration of the recommendations and the conclusions of the report. No specific date has been set at this time.
(2) Will the minister inform the House about the proposed schedule for the recommencement of production of the HBI plant in Port Hedland? Hon KEN TRAVERS replied : I thank the member for some notice of this question. I am advised - (1) The report requisitioned by the State Mining Engineer from Boodarie Iron, under section 45 of the Mines Safety and Inspection Act 1994, is currently due to be submitted on 30 November 2004. (2) Recommencement by Boodarie Iron of production from the HBI plant will be dependent upon full consideration of the recommendations and the conclusions of the report. No specific date has been set at this time.
Hon KEN TRAVERS replied : I thank the member for some notice of this question. I am advised - (1) The report requisitioned by the State Mining Engineer from Boodarie Iron, under section 45 of the Mines Safety and Inspection Act 1994, is currently due to be submitted on 30 November 2004. (2) Recommencement by Boodarie Iron of production from the HBI plant will be dependent upon full consideration of the recommendations and the conclusions of the report. No specific date has been set at this time.
I thank the member for some notice of this question. I am advised - (1) The report requisitioned by the State Mining Engineer from Boodarie Iron, under section 45 of the Mines Safety and Inspection Act 1994, is currently due to be submitted on 30 November 2004. (2) Recommencement by Boodarie Iron of production from the HBI plant will be dependent upon full consideration of the recommendations and the conclusions of the report. No specific date has been set at this time.
(1) The report requisitioned by the State Mining Engineer from Boodarie Iron, under section 45 of the Mines Safety and Inspection Act 1994, is currently due to be submitted on 30 November 2004. (2) Recommencement by Boodarie Iron of production from the HBI plant will be dependent upon full consideration of the recommendations and the conclusions of the report. No specific date has been set at this time.
(2) Recommencement by Boodarie Iron of production from the HBI plant will be dependent upon full consideration of the recommendations and the conclusions of the report. No specific date has been set at this time.