Hon Dr Steve Thomas requests detailed financial information on Western Power projects exceeding $2 million, but Western Power redacts project descriptions citing customer confidentiality, providing only aggregated financial data.

AnsweredQoN 2137Legislative Council
Asked
20 August 2024
Portfolio
Energy

QuestionView source ↗

I refer to Budget Paper 2 Volume
2, page 791 of the 2024 May State Budget, which outlines the works in progress
under Western Power, and for the financial year 2023-24 in each category of Distribution Capacity Expansion, Distribution Customer Access, Transmission Capacity Expansion, and Transmission Customer Driven, I ask: (a) please provide a list of all projects with a budget over $2 million; and (b) for each project listed under (a), please provide: (i) the budget for the project when it commenced; (ii) the current budget for the project; (iii) how much has been spent on the project to date; and (iv) what blowouts, in dollar amounts, have occurred in delivering the project to date?

AnswerView source ↗

Answered
15 October 2024
Responded by
Parliamentary Secretary to the Minister for Energy
Response time
9 days
a) – (b) Western Power cannot share customer information – all project descriptions in the tables have therefore been redacted.
Distribution Capacity Expansion
Capacity expansion projects for the distribution network address future loading and voltage obligations on Western Power’s customer load demand. Capacity Expansion investment is necessary to cater for load growth while preventing premature ageing of assets.
$ Million
Project description
Budget when commenced
Current Budget
Inception to date spend
(August)
REDACTED
9.4
9.4
7.4
REDACTED
8.0
12.5 1
6.8
REDACTED
1.5
2.2 1
2.1
REDACTED
1.9
1.9
1.3
REDACTED
7.5
7.5
0.7
REDACTED
10.4
10.4
10.1
1.    Budget changes resulted from changes in project scope.
Distribution Customer Access
Customer-initiated work on the distribution network including connecting new customers, upgrading existing connections and subdivisions, and which is partly funded by the customer. This category of investment generally includes high-volume, low-cost projects.
Transmission Capacity Expansion
Investment for the purposes of increasing the capacity of transmission assets or construction of new assets to meet the growth in network peak demand.
$ Million
Project description
Budget when commenced
Current Budget
Inception to date spend
(August)
REDACTED
8.0
8.0
2.8
REDACTED
3.7
3.7
4.4 1
REDACTED
13.9
13.9
2.3
1.      Cost changes resulted from changes to project scope
Transmission Customer Driven
Customer-initiated work for transmission includes projects for transmission assets relocation and new large load connections such as wind and solar farms and batteries.
The budgets for these projects develop as the projects progress, with variations to budget driven by customer-related reasons.
$ Million
Project description
Budget when commenced
Current project Budget
Inception to date spend
(August)
REDACTED
1.9
7.0
6.0
REDACTED
23.3
30.0
2.6
REDACTED
4.3
5.1
4.9
REDACTED
4.2
6.3
5.5
REDACTED
16.1
17.6
17.9
REDACTED
3.2
3.3
0.8
REDACTED
16.0
16.0
2.8