Question regarding the allocation of Road Trauma Trust Account funds to Main Roads WA for metropolitan intersection crash projects in the 2013-2014 financial year. The answer details specific project allocations and timelines.

AnsweredQoN 1900Legislative Assembly
Asked
25 February 2014
Portfolio
Road Safety

QuestionView source ↗

(1) How much money from the Road Trauma Trust Account (RTTA) was allocated to Main Roads Western Australia (MRWA) in the 2013–2014 financial year under the heading Metropolitan Intersection Crashes - state and local roads? (2) How much of that money has been allocated to state roads? (3) How much of that money has been allocated to local roads? (4) What specific projects has the money been allocated to and how much has been allocated for each project? (5) For each project will you please advise whether that is the total cost of the project and if not what the total cost of the project is?

AnswerView source ↗

Answered
1 April 2014
Responded by
Minister for Road Safety
Response time
35 days
(1) $12.05m was originally allocated to the Metropolitan Intersection Safety Program in the 2013/14 Budget. As a result of project works timing, $5.5m was reallocated to the Regional Roads Improvement Program, leaving a total allocation of $6.525m.
(2) $6.525m.
(3) Nil.
(4) See (5).
(5) The following projects have been committed over a number of years:
(a)  Ennis Avenue/Grange Drive/Elanora Drive - a total of $1.9m has been committed over three years comprising $0.2m in 2012-13 and $1.7m in 2014-15.
(b)  Albany Highway/Liege Street - a total of $3.4m has been committed over three years comprising $0.1m in 2012-13, $1.1m in 2013-14 and $2.2m in 2014-15.
(c)  Reid Highway/Lord Street - a total of $8.0m has been committed over three years comprising $2.0m in 2012-13, $5.5m in 2013-14 and $0.5m in 2014-15.
(d)  Roe Highway/Berkshire Road- a total of $15m has been committed over three years comprising $0.6m in 2012-13 and $14.4m in 2014-15.
(e)  Guildford Road/Tonkin Highway - a total of $3m has been committed over future years comprising $0.15m in 2012-13 and $2.85m in future years.
(f) Ennis Avenue/Port Kennedy Drive - a total of $3m has been committed over future years comprising $0.15m in 2013-14 and $2.85 in future years.
(g)  Marmion Avenue/Mullaloo Drive - a total of $2m has been committed over future years comprising $0.15m in 2013-14 and $1.85 in future years.
(h)  Wanneroo Road/Hepburn Avenue - a total of $5m has been committed over future years comprising $0.15m in 2013-14 and $4.85m in future years.