❓ Hon Stephen Dawson asks about the Karratha City Centre Infrastructure Works Project (KCCIWP), including funding breakdowns, timelines, and completion status of stages 1 and 2. The Minister provides details on funding allocations, project scopes, timelines, and expenditures for both stages.
AnsweredQoN 2275Legislative Council
QuestionView source ↗
I refer to the former Minister for Regional Development's media statement of 30 November 2013, and its reference to the "$110 million KCCIW Stage 2", and I ask: (a) will the Minister for Regional Development provide a breakdown of the $110 million in terms of: (i) individual projects; (ii) timeframes for commencement and completion; and (iii) funds allocated to each project; (b) has the KCCIW Stage 1 been fully completed and, if so, what was the final expenditure; and (c) if no to (b): (i) how much has been allocated to Stage 1; and (ii) much has been expended to date?
AnswerView source ↗
Answered
10 March 2015
Responded by
Parliamentary Secretary representing the Minister for Regional Development
Response time
97 days
(a) (i) Cabinet approved funding of $111 million for the Karratha City Centre Infrastructure Works Project (KCCIWP) Stage 2. The funding allocation is to deliver Stages 2A and 2B of the KCCIWP.
Stage 2A will undertake design works associated with the development of the Karratha Health Campus (KHC) site and surrounding roads and infrastructure. Works include approvals for the creation of the site, design, and approvals of external services (including power, water, sewer and telecommunication services), design and approvals for road modification and realignment works for road access to the KHC site. Funding also provided for the acquisition and preparation of the first three key city centre sites directly opposite the Karratha Quarter precinct on Sharpe Ave to assist with accelerating revitalisation of the city centre.
Stage 2B works will be for the earth and civil works for the development of the KHC site and surrounding roads and infrastructure.
(ii) Stage 2 commenced in April 2013 with an expected completion date of 30 June 2017.
(iii) Stage 2A - $30 million was approved by Cabinet on 10 December 2012
Stage 2B - $81 million was approved by Cabinet on 5 August 2013.
(b) No.
(c) (i) $74.6 million has been allocated to complete Stage 1.
(ii) $65.538 million.
Stage 2A will undertake design works associated with the development of the Karratha Health Campus (KHC) site and surrounding roads and infrastructure. Works include approvals for the creation of the site, design, and approvals of external services (including power, water, sewer and telecommunication services), design and approvals for road modification and realignment works for road access to the KHC site. Funding also provided for the acquisition and preparation of the first three key city centre sites directly opposite the Karratha Quarter precinct on Sharpe Ave to assist with accelerating revitalisation of the city centre.
Stage 2B works will be for the earth and civil works for the development of the KHC site and surrounding roads and infrastructure.
(ii) Stage 2 commenced in April 2013 with an expected completion date of 30 June 2017.
(iii) Stage 2A - $30 million was approved by Cabinet on 10 December 2012
Stage 2B - $81 million was approved by Cabinet on 5 August 2013.
(b) No.
(c) (i) $74.6 million has been allocated to complete Stage 1.
(ii) $65.538 million.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.