❓ A WA parliamentary question seeks details on the State and Federal contributions, budget variations, and expected completion date for Stage 2 of the Central TAFE redevelopment project in the William and Aberdeen Streets area.
AnsweredQoN 2496Legislative Assembly
QuestionView source ↗
In relation to Stage 2 of Central TAFE redevelopment on the corner of William and Aberdeen Streets in my electorate, I ask:
(a) what is the State Government’s contribution;
(b) what is the Federal contribution;
(c) what was the original budget (and State-Federal contributions) and on what dates have cost variations been made; and
(d) what is the expected completion date?
(a) what is the State Government’s contribution;
(b) what is the Federal contribution;
(c) what was the original budget (and State-Federal contributions) and on what dates have cost variations been made; and
(d) what is the expected completion date?
AnswerView source ↗
Answered
20 April 2010
Responded by
Minister representing the Minister for Energy; Training and Workforce Development
Response time
34 days
(a) $30,970,000.
(b) $28,557,066.
(c) The original total budget as at 1 July 2007 totalled $38,042,000 ($28,557,066 Federal and $9,484,934 State).
In response to the construction tender process the Department of Education and Training, under the previous Labor Government (in April 2008) approved a total budget increase of $59,527,066 ($28,577,066 Federal and $30,970,000 State).
(d) Construction completion is expected in October 2010 and internal fit?out by February 2011.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
(b) $28,557,066.
(c) The original total budget as at 1 July 2007 totalled $38,042,000 ($28,557,066 Federal and $9,484,934 State).
In response to the construction tender process the Department of Education and Training, under the previous Labor Government (in April 2008) approved a total budget increase of $59,527,066 ($28,577,066 Federal and $30,970,000 State).
(d) Construction completion is expected in October 2010 and internal fit?out by February 2011.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.