❓ Ms. Saffioti questions the Finance portfolio regarding the New Buildings program's on-time delivery rate, seeking details on projects delivered outside the approved timeframe and the extent of the delays. The answer refers to a tabled paper.
AnsweredQoN 34Legislative Assembly
QuestionView source ↗
I refer to page 442 of the 2012-2013 Budget papers, Volume 2, which states that only 74 per cent of the New Buildings program was delivered within three months of the approved timeframe, and ask:
(a) which projects were delivered outside the approved timeframe; and
(b) how many months or years was each individual project outside its approved timeframe?
(a) which projects were delivered outside the approved timeframe; and
(b) how many months or years was each individual project outside its approved timeframe?
AnswerView source ↗
Answered
15 May 2013
Responded by
Minister for Finance
Response time
28 days
(a)-(b) Please see tabled paper no .....
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.