A WA parliamentary question seeks details on contracts related to the James Street Bus Bridge construction, and the Minister provides a breakdown of four contracts including costs, timelines, and contractors involved.

AnsweredQoN 4129Legislative Assembly
Asked
12 October 2010
Portfolio
Transport

QuestionView source ↗

For each contract required for the construction of the bus bridge over Roe Street and the railway line connecting Northbridge and the city:
(a) who was awarded the contract;
(b) what was delivered under each particular contract;
(c) what was the date the contract was awarded;
(d) what was the practical completion date of the contract;
(e) what was the cost of the work when the contract was awarded;
(f) what was the full cost for all work associated with that contract?

AnswerView source ↗

Answered
9 November 2010
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
28 days
The James Street Bus Bridge project was undertaken in two stages.  One involved the construction of the main structure spanning Roe Street and the rail lines.  The second stage of the work required, modification of James and Fitzgerald Streets, and the bus way adjacent to the new Arena Perth site to accommodate bus movements.
Insofar as the Public Transport Authority is concerned four contracts were awarded. The details of each of those contracts are as follows -
Contract 1
(a) BGC Constuction.
(b) Building of the Bus Bridge as a Design and Construct variation to the Building Management and Works (CMW) Perth Arena Contract.
(c) 31 October 2007.
(d) 4 August 2010.
(e) $14,801,793 (inc GST).
(f) $15,350,210 (inc GST).
Contract 2
(a) Downer EDI Works.
(b) Realignment of the Southern Bus Way to feed onto the new Bus Bridge structure.
(c) 28 June 2010.
(d) 10 September 2010.
(e) $331,754 (inc GST).
(f) $456,714.00 (inc GST).
Contract 3
(a) Brajkovich Demolition.
(b) Removed the existing Main Roads building on James Street to make way for the Bus Bridge ramp.
(c) early April 2010.
(d) 26 June 2010.
(e) $20,680 (inc GST).
(f) $42,638 (inc GST).
Contract 4
(a) Densford Civil Pty Ltd.
(b) Modification works to James Street required to connect the new Bus Bridge to Fitzgerald Street.
(c) 15 July 2010.
(d) Current anticipated Stage 1 completed is the 2
nd
week of December 2010.
(e) $1,516,194 (inc GST).
(f) Projected adjusted contract value (to date) is estimated at $1 800 000 (inc GST). This includes refundable amounts of around $252,000 for upgrade works for the City of Perth and Main Roads infrastructure which has now been included within the Public Transport Authority's James Street road works contract.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on