Question regarding the timeline for platform extensions on the Currambine line to accommodate new three-car rail sets, with a detailed response outlining the tender and construction schedule.

AnsweredQoN 1077Legislative Assembly
Asked
27 February 2003
Portfolio
Planning and Infrastructure

QuestionView source ↗

I refer to the new railcars for the Currambine line, scheduled for delivery in 2004 and ask will the Minister advise when will the platforms along this line be lengthened, in order to accommodate the new three-car set configuration?

AnswerView source ↗

Answered
3 June 2003
Responded by
Minister for Planning and Infrastructure
Response time
96 days
Public tenders were called on 15 March 2003 for the platform extensions. Tenders close in mid-April and the contract for the works will be awarded in June. Construction works will commence in July this year and will be complete by August 2004.