❓ Hon Lynn MacLaren asks about the status of conditions related to the Roe Highway Stage 8 approval, and the planned start of construction. The response lists completed conditions and states remaining conditions are ongoing or outstanding, with initial construction activity details pending.
AnsweredQoN 1327Legislative Council
QuestionView source ↗
ROE HIGHWAY STAGE 8 — IMPLEMENTATION
CONDITIONS
1327. Hon LYNN MacLAREN to the
parliamentary secretary representing the Minister for Transport:
I refer to statement 1008 published
on 2 July 2015, which relates to approval for Roe 8 under the Environmental Protection
Act.
(1) Will the
minister please list, by number, each of the conditions that remain outstanding
and each that have been completed?
(2) Regarding the
proposed December start to construction, what will be the first works to be
begun, and in which location?
CONDITIONS
1327. Hon LYNN MacLAREN to the
parliamentary secretary representing the Minister for Transport:
I refer to statement 1008 published
on 2 July 2015, which relates to approval for Roe 8 under the Environmental Protection
Act.
(1) Will the
minister please list, by number, each of the conditions that remain outstanding
and each that have been completed?
(2) Regarding the
proposed December start to construction, what will be the first works to be
begun, and in which location?
AnswerView source ↗
On behalf of the Parliamentary Secretary
to the Minister for Transport, I thank the member for some notice of the question.
(1) The following
conditions have been satisfied: 4–1, 4–2, 7–6, 7–7,
8–2, 10–2, 10–3, 10–4, 12–6, 12–7,
12–8, 12–11, 12–12, 12–14 and 12–15.
All remaining conditions are either
ongoing or outstanding. It is to be noted that Main Roads is compliant to date
with the conditions of MS 1008.
(2) Initial
construction activity will be outlined in the alliance team's early
works schedule, which is currently being finalised.
to the Minister for Transport, I thank the member for some notice of the question.
(1) The following
conditions have been satisfied: 4–1, 4–2, 7–6, 7–7,
8–2, 10–2, 10–3, 10–4, 12–6, 12–7,
12–8, 12–11, 12–12, 12–14 and 12–15.
All remaining conditions are either
ongoing or outstanding. It is to be noted that Main Roads is compliant to date
with the conditions of MS 1008.
(2) Initial
construction activity will be outlined in the alliance team's early
works schedule, which is currently being finalised.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.