Hon George Cash asks about potential delays and cost impacts to the Mandurah Bypass road project. Hon Adele Farina responds that the project is on schedule and within budget.

AnsweredQoN 74Legislative Council
Asked
25 February 2008
Portfolio
Planning and Infrastructure

QuestionView source ↗

PERTH-BUNBURY HIGHWAY — DELAYS TO MANDURAH BYPASS
(1) Which parts of the respective contracts relating to the Mandurah bypass road are currently behind schedule? (2) Will these delays affect the previously announced completion date? (3) Will these delays impact on the cost of the project; and, if so, by how much? Hon ADELE FARINA

AnswerView source ↗

I thank the honourable member for some notice of this question. (1) The new Perth-Bunbury highway project alliance contract is on schedule for completion by the previously announced opening date of late 2009. (2)-(3) Not applicable.
(2) Will these delays affect the previously announced completion date? (3) Will these delays impact on the cost of the project; and, if so, by how much? Hon ADELE FARINA replied: I thank the honourable member for some notice of this question. (1) The new Perth-Bunbury highway project alliance contract is on schedule for completion by the previously announced opening date of late 2009. (2)-(3) Not applicable.
(3) Will these delays impact on the cost of the project; and, if so, by how much? Hon ADELE FARINA replied: I thank the honourable member for some notice of this question. (1) The new Perth-Bunbury highway project alliance contract is on schedule for completion by the previously announced opening date of late 2009. (2)-(3) Not applicable.
Hon ADELE FARINA replied: I thank the honourable member for some notice of this question. (1) The new Perth-Bunbury highway project alliance contract is on schedule for completion by the previously announced opening date of late 2009. (2)-(3) Not applicable.
I thank the honourable member for some notice of this question. (1) The new Perth-Bunbury highway project alliance contract is on schedule for completion by the previously announced opening date of late 2009. (2)-(3) Not applicable.
(1) The new Perth-Bunbury highway project alliance contract is on schedule for completion by the previously announced opening date of late 2009. (2)-(3) Not applicable.
(2)-(3) Not applicable.