❓ Mr. Cook inquires about planned maintenance and building works for several primary schools. The Minister responds with specific funding for Medina Primary and general air-cooling plans, along with projected routine maintenance costs for all listed schools.
AnsweredQoN 6431Legislative Assembly
QuestionView source ↗
Can the Minister please provide details of anticipated routine maintenance and any building planned in the years 2011–12, 2012–13, and 2013–2014 for the following schools:
(a) Medina Primary School;
(b) Calista Primary School;
(c) Orelia Primary School;
(d) North Parmelia Primary School;
(e) Bertram Primary School;
(f) Leda Primary School; and
(g) Baldivis Primary School?
(a) Medina Primary School;
(b) Calista Primary School;
(c) Orelia Primary School;
(d) North Parmelia Primary School;
(e) Bertram Primary School;
(f) Leda Primary School; and
(g) Baldivis Primary School?
AnswerView source ↗
Answered
22 November 2011
Responded by
Minister for Education
Response time
33 days
Capital Works:
(a) MedinaPrimary School- funding of $925 000 allocated in 2011-12 for an administration upgrade
(b) CalistaPrimary School- no works
(c) OreliaPrimary School- no works
(d) North Parmelia Primary School - no works
(e) BertramPrimary School- no works
(f) LedaPrimary School- no works
(g) BaldivisPrimary School- no works
Air-cooling will be provided to spaces in all of the above schools that are currently not air-cooled. It is anticipated that this will occur during year 3 of the program to be completed in 2013-14. The Department of Education is not yet able to estimate the cost of the air-cooling until the detailed audit is undertaken. This is expected to occur in late 2012 or early 2013.
The projected expenditure for routine maintenance* is anticipated as:
(a) MedinaPrimary School
2011/2012 - $6 484
2012/2013 - $6 678
2013/2014 - $6 879
(b) CalistaPrimary School
2011/2012 - $9 663
2012/2013 - $9 953
2013/2014 - $10 252
(c) OreliaPrimary School
2011-12 - $11 427
2012-13 - $11 770
2013-14 - $12 123
(d) NorthParmeliaPrimary School
2011-12 - $5 387
2012-13 - $5 549
2013-14 - $5 715
(e) BertramPrimary School
2011-12 - $5 539
2012-13 - $5 705
2013-14 - $5 876
(f) LedaPrimary School
2011-12 - $5 044
2012-13 - $5 196
2013-14 - $5 351
(g) BaldivisPrimary School
2011-12 - $5 425
2012-13 - $5 588
2013-14 - $5 756
*Routine maintenance is a category of the Building Maintenance Program and includes all maintenance which is required by law, by regulation or has high consequence if not addressed. Types of works covered under this category include gutter cleaning, RCD testing, emergency lighting and fire equipment servicing and inspections, fire breaks, irrigation servicing and testing of portable electrical equipment.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
(a) MedinaPrimary School- funding of $925 000 allocated in 2011-12 for an administration upgrade
(b) CalistaPrimary School- no works
(c) OreliaPrimary School- no works
(d) North Parmelia Primary School - no works
(e) BertramPrimary School- no works
(f) LedaPrimary School- no works
(g) BaldivisPrimary School- no works
Air-cooling will be provided to spaces in all of the above schools that are currently not air-cooled. It is anticipated that this will occur during year 3 of the program to be completed in 2013-14. The Department of Education is not yet able to estimate the cost of the air-cooling until the detailed audit is undertaken. This is expected to occur in late 2012 or early 2013.
The projected expenditure for routine maintenance* is anticipated as:
(a) MedinaPrimary School
2011/2012 - $6 484
2012/2013 - $6 678
2013/2014 - $6 879
(b) CalistaPrimary School
2011/2012 - $9 663
2012/2013 - $9 953
2013/2014 - $10 252
(c) OreliaPrimary School
2011-12 - $11 427
2012-13 - $11 770
2013-14 - $12 123
(d) NorthParmeliaPrimary School
2011-12 - $5 387
2012-13 - $5 549
2013-14 - $5 715
(e) BertramPrimary School
2011-12 - $5 539
2012-13 - $5 705
2013-14 - $5 876
(f) LedaPrimary School
2011-12 - $5 044
2012-13 - $5 196
2013-14 - $5 351
(g) BaldivisPrimary School
2011-12 - $5 425
2012-13 - $5 588
2013-14 - $5 756
*Routine maintenance is a category of the Building Maintenance Program and includes all maintenance which is required by law, by regulation or has high consequence if not addressed. Types of works covered under this category include gutter cleaning, RCD testing, emergency lighting and fire equipment servicing and inspections, fire breaks, irrigation servicing and testing of portable electrical equipment.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.