❓ Mr. Snook inquires about the timeline and funding for upgrades to public boat ramps at Tantabiddi and Bundegi. The Minister responds with details on the project's progress, funding allocation, and planned commencement of construction at Bundegi.
AnsweredQoN 1419Legislative Assembly
QuestionView source ↗
point 16, can the Minister inform the Parliament what the estimated timeline and where the funding is for the upgrade of the public boat ramps at Tantabiddi and Bundegi to improve trailer boat access to Exmouth waters?
Quotes have been sought through DPI's Panel Contract to engage a consultant to undertake detailed designs and assist with construction of the boat ramp upgrade at Bundegi. Construction is planned to commence in April 2007, subject to design and approvals. Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi. Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Construction is planned to commence in April 2007, subject to design and approvals. Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi. Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi. Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Quotes have been sought through DPI's Panel Contract to engage a consultant to undertake detailed designs and assist with construction of the boat ramp upgrade at Bundegi. Construction is planned to commence in April 2007, subject to design and approvals. Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi. Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Construction is planned to commence in April 2007, subject to design and approvals. Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi. Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi. Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
AnswerView source ↗
Answered
21 September 2006
Responded by
Minister for Planning and Infrastructure
Response time
29 days
The Shire of Exmouth is the proponent for the boat ramps, and the Department for Planning and Infrastructure (DPI) is providing assistance to the Shire with this boating infrastructure upgrade.
Quotes have been sought through DPI's Panel Contract to engage a consultant to undertake detailed designs and assist with construction of the boat ramp upgrade at Bundegi.
Construction is planned to commence in April 2007, subject to design and approvals.
Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi.
Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Quotes have been sought through DPI's Panel Contract to engage a consultant to undertake detailed designs and assist with construction of the boat ramp upgrade at Bundegi.
Construction is planned to commence in April 2007, subject to design and approvals.
Quotes have also been sought for detailed designs for boat ramp upgrades at Tantabiddi. The timing for works at Tantabiddi is yet to be determined, but would occur after Bundegi.
Dedicated government funding of $1.5 million was allocated for these projects and is being held by DPI.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.