Hon Ray Halligan asked about the planned primary school in Hocking. Hon Ljiljanna Ravlich confirmed the school's construction commenced on 1 May 2007, with completion and student intake expected in 2008, at a cost of $8.8 million.

AnsweredQoN 265Legislative Council
Asked
8 May 2007
Portfolio
Education and Training

QuestionView source ↗

HOCKING PRIMARY SCHOOL
(1) Is a primary school planned for Hocking? (2) If so, when will work on the school begin? (3) If so, when will the school be completed? (4) When will it take its first students? (5) What is the estimated cost? Hon LJILJANNA RAVLICH

AnswerView source ↗

I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(2) If so, when will work on the school begin? (3) If so, when will the school be completed? (4) When will it take its first students? (5) What is the estimated cost? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(3) If so, when will the school be completed? (4) When will it take its first students? (5) What is the estimated cost? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(4) When will it take its first students? (5) What is the estimated cost? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(5) What is the estimated cost? Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
Hon LJILJANNA RAVLICH replied: I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
I thank the member for some notice of this question. On behalf of the Minister for Education and Training, I am happy to provide the following response - (1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(1) Yes. (2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(2) Construction commenced on 1 May 2007. (3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(3) The school will be ready for the commencement of the 2008 school year. (4) 2008. (5) The budget allocation is $8.8 million.
(4) 2008. (5) The budget allocation is $8.8 million.