❓ Hon. C.L. Edwardes asks about the status of conditions set for Western Australia Beach and Golf Resort Pty Ltd (WABGR) assignment. The Minister responds that WABGR has satisfied all conditions, including priority works, bond provision, creditor payments, and sub-lease honoring.
AnsweredQoN 1743Legislative Assembly
QuestionView source ↗
(b) which of the conditions appeared to have been met; (c) in what way do they appear to have been met; (d) which of the conditions are yet to be met by WABGR; (e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(c) in what way do they appear to have been met; (d) which of the conditions are yet to be met by WABGR; (e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(d) which of the conditions are yet to be met by WABGR; (e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
· taking an assignment of the project as currently approved, without any changes to the State Agreement or ratifying Act; · completing a program of priority works to enhance public access and amenity and revitalise the project area; · providing a bond of $1million in favour of the State to secure completion of the priority works; · paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· completing a program of priority works to enhance public access and amenity and revitalise the project area; · providing a bond of $1million in favour of the State to secure completion of the priority works; · paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· providing a bond of $1million in favour of the State to secure completion of the priority works; · paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
(b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
(c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
(d) See (a) above. (e) Not applicable. (f) Not applicable.
(e) Not applicable. (f) Not applicable.
(f) Not applicable.
(c) in what way do they appear to have been met; (d) which of the conditions are yet to be met by WABGR; (e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(d) which of the conditions are yet to be met by WABGR; (e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(e) what time line is in place for the completion of the out standing conditions; and (f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
(f) what action will the Minister take if the WABGR fail to complete the out standing conditions?
· taking an assignment of the project as currently approved, without any changes to the State Agreement or ratifying Act; · completing a program of priority works to enhance public access and amenity and revitalise the project area; · providing a bond of $1million in favour of the State to secure completion of the priority works; · paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· completing a program of priority works to enhance public access and amenity and revitalise the project area; · providing a bond of $1million in favour of the State to secure completion of the priority works; · paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· providing a bond of $1million in favour of the State to secure completion of the priority works; · paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· paying all trade creditors of PKR; and · honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
· honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000. (b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
(b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed. (c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
(c) See (b) above. (d) See (a) above. (e) Not applicable. (f) Not applicable.
(d) See (a) above. (e) Not applicable. (f) Not applicable.
(e) Not applicable. (f) Not applicable.
(f) Not applicable.
AnswerView source ↗
Answered
9 September 2003
Responded by
Minister for Planning and Infrastructure
Response time
28 days
(a) Western Australia Beach and Golf Resort Pty Ltd (WABGR) has satisfied all of the conditions of assignment set by Government in August 2002, including
· taking an assignment of the project as currently approved, without any changes to the State Agreement or ratifying Act;
· completing a program of priority works to enhance public access and amenity and revitalise the project area;
· providing a bond of $1million in favour of the State to secure completion of the priority works;
· paying all trade creditors of PKR; and
· honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000.
(b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed.
(c) See (b) above.
(d) See (a) above.
(e) Not applicable.
(f) Not applicable.
· taking an assignment of the project as currently approved, without any changes to the State Agreement or ratifying Act;
· completing a program of priority works to enhance public access and amenity and revitalise the project area;
· providing a bond of $1million in favour of the State to secure completion of the priority works;
· paying all trade creditors of PKR; and
· honouring the terms of the sub-lease that was issued by PKR to The Golf Club (WA) Ltd in June 2000.
(b) At the time of the media statement, WABGR’s project manager Mirvac Fini had advised that the program of priority works was complete, however the Department for Planning Infrastructure and the City of Rockingham had yet to formally inspect the works. That inspection has now been carried out and completion of the works has been confirmed.
(c) See (b) above.
(d) See (a) above.
(e) Not applicable.
(f) Not applicable.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.